Putting up a stud wall?
See inside a stud wall, before it’s boarded up
A new partition looks the same from outside whether it’s built well or badly. Watch a real steel stud wall go up in 3D, in the order your builder will build it, and see what to check before each side is boarded.
- 9 stages, in build order
- 10 checks before it’s hidden
- Sourced to regulations and makers
Interactive 3D modelThe order it goes in
Once the second side is boarded, nothing inside can be checked. Knowing the order tells you when to look.
1Channels top and bottom
A steel channel is fixed to the floor and a deeper one to the floor above, on the line of the new wall.
2Studs
Steel studs slide into both channels, no more than 600 mm apart. Under a floor that can move, they stop just short of the top channel.
3The door opening
The floor channel turns up each side of the opening and a channel spans the head. Timber lines the opening so the door frame has something solid to fix to.
4First fix
Cables run through the holes punched in the studs to boxes held on short channels between them. Plywood goes in wherever something heavy will hang.
5One side boarded
Plasterboard goes on one face, the sheets standing on end with their joints on studs.
6Insulation
Mineral wool fills the spaces between the studs. It's what makes a stud wall quiet.
7The other side boarded
The second face is boarded, its joints staggered from the first side's. From here on the inside of the wall can't be seen.
8Skim, ceiling and floor
The boards are skimmed, the ceilings finished and the floor laid.
9Door, trim and second fix
The door lining is packed and fixed to the timber, the door hung, then architraves and skirting. Last, the sockets and switches go on their boxes.
Check it before it’s covered up
These are the things a finished wall won’t show you. Each one is in the 3D model, so you can see what good looks like before you check your own.
0 of 10 checked

After stage 6
Before the second side is boarded
Studs no more than 600 mm apart, standing in both channels
Every stud should sit in the floor channel and the top channel. Wider spacing makes a wall that flexes and cracks at the joints.
Room to move at the top, under a floor that can deflect
Where the floor above can sag a little under load, the studs stop short of the top channel and aren't fixed to it, and the boards are fixed to a strap below the channel. Otherwise the floor bears on the wall and cracks it.
Something solid behind anything heavy
Plasterboard alone won't hold a TV bracket, a radiator, wall cupboards or a loaded shelf. Plywood should be fixed between the studs wherever they'll go. In the model, 18 mm plywood sits behind the shelf.
A door opening that's stiffened and lined
At each side of a door the floor channel should turn up the jamb, with a channel across the head and timber lining the opening. A door frame screwed to bare steel will work loose.
Cables only where they'd be expected
Hidden cables should run straight across, or straight up or down, from a socket or switch, and pass through the studs' own holes with a grommet so the steel can't cut them. In a metal stud wall the circuits also need 30 mA RCD protection.
Sockets and switches at a height you can reach
Approved Document M puts them between 450 and 1200 mm from the floor in new homes, a good rule anywhere. Each box should be held on a length of channel fixed between the studs, not just clamped to the board.
Insulation filling the gaps
Mineral wool between the studs, with no gaps, is what stops sound. In new homes Approved Document E sets a sound standard for walls round bedrooms and rooms with a WC, which a stud wall usually needs insulation to meet.

After stage 7
Before it's skimmed
Boards on end, joints on studs and staggered
Each sheet's long edges should land on a stud, and the joints on one side shouldn't line up with those on the other, or with the edges of the door opening.
Sealant round the edges and the boxes
A bead of sealant where the boards meet the floor and ceiling, and round each socket box, stops sound getting round the wall.

After stage 8
Before the door goes on
If it's a fire door, the whole set is
Your building control officer will say whether a door must be a fire door. If it must, the leaf, frame, seals, hinges and closer are certified as one set: look for the certification label, the intumescent strip in the frame and three hinges.
A guide to what to look for, not a substitute for your building control officer or a registered electrician.

See it for yourself
Turn it, pull it apart, and tap any part to see what it is and how it’s specified.
Open the stud wall in 3DMore guides
Renovating more than one room?
A new part of the house goes up in 3D most weeks: kitchens, doors, extensions, bathrooms. Get each one by email, with what to check before it’s hidden.