Putting up a stud wall?

See inside a stud wall, before it’s boarded up

A new partition looks the same from outside whether it’s built well or badly. Watch a real steel stud wall go up in 3D, in the order your builder will build it, and see what to check before each side is boarded.

  • 9 stages, in build order
  • 10 checks before it’s hidden
  • Sourced to regulations and makers
The stud wall model, cut away to show the steel studs, boards, insulation and the doorInteractive 3D model

The order it goes in

Once the second side is boarded, nothing inside can be checked. Knowing the order tells you when to look.

  1. The stud wall at stage 1: channels top and bottom1

    Channels top and bottom

    A steel channel is fixed to the floor and a deeper one to the floor above, on the line of the new wall.

  2. The stud wall at stage 2: studs2

    Studs

    Steel studs slide into both channels, no more than 600 mm apart. Under a floor that can move, they stop just short of the top channel.

  3. The stud wall at stage 3: the door opening3

    The door opening

    The floor channel turns up each side of the opening and a channel spans the head. Timber lines the opening so the door frame has something solid to fix to.

  4. The stud wall at stage 4: first fix4

    First fix

    Cables run through the holes punched in the studs to boxes held on short channels between them. Plywood goes in wherever something heavy will hang.

  5. The stud wall at stage 5: one side boarded5

    One side boarded

    Plasterboard goes on one face, the sheets standing on end with their joints on studs.

  6. The stud wall at stage 6: insulation6

    Insulation

    Mineral wool fills the spaces between the studs. It's what makes a stud wall quiet.

  7. The stud wall at stage 7: the other side boarded7

    The other side boarded

    The second face is boarded, its joints staggered from the first side's. From here on the inside of the wall can't be seen.

  8. The stud wall at stage 8: skim, ceiling and floor8

    Skim, ceiling and floor

    The boards are skimmed, the ceilings finished and the floor laid.

  9. The stud wall at stage 9: door, trim and second fix9

    Door, trim and second fix

    The door lining is packed and fixed to the timber, the door hung, then architraves and skirting. Last, the sockets and switches go on their boxes.

Watch every step in 3D, with captions →

Check it before it’s covered up

These are the things a finished wall won’t show you. Each one is in the 3D model, so you can see what good looks like before you check your own.

0 of 10 checked

After stage 6

Before the second side is boarded

  • Studs no more than 600 mm apart, standing in both channels

    Every stud should sit in the floor channel and the top channel. Wider spacing makes a wall that flexes and cracks at the joints.

    British Gypsum GypWall Single Frame; The Site BookMetal studs →

  • Room to move at the top, under a floor that can deflect

    Where the floor above can sag a little under load, the studs stop short of the top channel and aren't fixed to it, and the boards are fixed to a strap below the channel. Otherwise the floor bears on the wall and cracks it.

    The Site Book, deflection heads (pp 12 to 14)Deflection head →

  • Something solid behind anything heavy

    Plasterboard alone won't hold a TV bracket, a radiator, wall cupboards or a loaded shelf. Plywood should be fixed between the studs wherever they'll go. In the model, 18 mm plywood sits behind the shelf.

    The Site Book, fixtures (p 10)Pattressing and noggings →

  • A door opening that's stiffened and lined

    At each side of a door the floor channel should turn up the jamb, with a channel across the head and timber lining the opening. A door frame screwed to bare steel will work loose.

    The Site Book, door details (p 29)Door frame →

  • Cables only where they'd be expected

    Hidden cables should run straight across, or straight up or down, from a socket or switch, and pass through the studs' own holes with a grommet so the steel can't cut them. In a metal stud wall the circuits also need 30 mA RCD protection.

    BS 7671 522.6.202 and 522.6.204Sockets and switches →

  • Sockets and switches at a height you can reach

    Approved Document M puts them between 450 and 1200 mm from the floor in new homes, a good rule anywhere. Each box should be held on a length of channel fixed between the studs, not just clamped to the board.

    Approved Document M; The Site Book, socket boxes

  • Insulation filling the gaps

    Mineral wool between the studs, with no gaps, is what stops sound. In new homes Approved Document E sets a sound standard for walls round bedrooms and rooms with a WC, which a stud wall usually needs insulation to meet.

    Approved Document E, requirement E2Acoustic insulation →

After stage 7

Before it's skimmed

  • Boards on end, joints on studs and staggered

    Each sheet's long edges should land on a stud, and the joints on one side shouldn't line up with those on the other, or with the edges of the door opening.

    British Gypsum GypWall Single FramePlasterboard →

  • Sealant round the edges and the boxes

    A bead of sealant where the boards meet the floor and ceiling, and round each socket box, stops sound getting round the wall.

    The Site Book

After stage 8

Before the door goes on

  • If it's a fire door, the whole set is

    Your building control officer will say whether a door must be a fire door. If it must, the leaf, frame, seals, hinges and closer are certified as one set: look for the certification label, the intumescent strip in the frame and three hinges.

    Approved Document B; the door maker's certificationDoor frame →

A guide to what to look for, not a substitute for your building control officer or a registered electrician.

See it for yourself

Turn it, pull it apart, and tap any part to see what it is and how it’s specified.

Open the stud wall in 3D